Hi,
I created a view and associated BO from the TaskDefinition table that allowed me to create an IQA to replicate a more user friendly PA task list. This allows us to find tasks much more easily using IQA search criteria functionality. However, I have noticed an issue with Alert display tasks opened from my IQA. When I open an alert display task from the IQA, the alert sets associated with the specific task don't show up when the task is opened (they do display correctly when the same task is opened from the built-in PA task list). I constructed the link in the IQA to be almost the same as that in the built-in list but there are a few small differences.

Example link from custom IQA task list:
ACN_FollowUp_ReturnedMail

Equivalent link in built-in PA task list:
ACN_FollowUp_ReturnedMail

Does anyone have any advice around this?

Many thanks,